COMMERCIAL PROJECTS
CANON AMERICAS HEADQUARTERS
Commercial
Year Completed: 2013

1 WORLD TRADE CENTER - STEAM UTILITY PROJECT
Office Building
Year Completed: 2011

650 MADISON AVENUE
Retail
Year Completed: 2011

COOLING TOWER REPAIR SERVICES
Service
Year Completed: 2011

55 WATER STREET
Chiller Service
Year Completed: 2010

40 WALL STREET
Chiller Service
Year Completed: 2010

200 WEST STREET - GOLDMAN SACHS
Office Building
Year Completed: 2008

300 MADISON AVENUE
Office Building
Year Completed: 2003

AOL TIME WARNER CENTER
Mixed Development
Year Completed: 2003

REUTERS BUILDING - 3 TIMES SQUARE
Office Building
Year Completed: 2000


Canon Americas Headquarters
Project Image
Other Images
Other Images
Other Images
Other Images
Other Images
Company Logo

Fresh Meadow Mechanical Corp.


Engineer: Flack & Kurtz

Construction Manager: Turner Construction Company

Owner: Canon USA



Description: A new five story, 700,000+ square feet office building.

Services Provided: Furnish and install; a 3000 ton chiller plant, two 12,300 MBH Boilers, four 2000 GPM condenser water pumps, four 1700 GPM chiller water pumps, three 800 GPM primary hot water pumps, three 800 GPM secondary hot water pumps, and thirteen CRAC units for the data center.

Heating System: Two 12,300 MBH natural gas fired fire tube boilers for the constant primary, variable secondary heating system.

Cooling SystemThree1000 ton chillers providing chilled water for the fan coil and blower coil units for the under floor air distribution system, and providing chilled water for the CRAC units for the data center.

Energy Conservation:
The building is seeking LEED Gold Certification.

CAD Render 1
CAD Render 2