Supply two (2) 130,000 PPH high pressure boilers, one (1) 450,000
PPH dearator, one (1) triplex #6 fuel oil heater/pumping
fuel skid, six (6) 20,000 gallon fuel oil tanks,
two (2) boiler feedwater pumps, two (2) steam turbines
and forced draft fans, new duplex compressed air
system, and replacement of all of the existing
high pressure steam main in the boiler room. In
order to install the (2) boilers, it was necessary
for them to be tripped up on end and riggined down
through the sidewalk to the basement.