New Office Building - 845,000 Square Feet, 42 Stories of Offices,
Retial space and Meeting rooms.
Services provided:
Complete installation of Heating and Air Conditioning System
as per plans and specifications.
Heating system:
A central heating plant that includes a pressure reducing steam station
to provide low pressure steam for domestic hot water heaters,
air handling units, steam-to-hot water heat exchangers and unit
heaters. Hot water is utilized for fan-coil units, a radiant
floor heating system and perimeter fin tube radiation.
Cooling system:
A central cooling plant that includes two (2) 1200 Ton and one (1)
400 Ton Electric Centrifugal Chillers located in the basement, a four
cell Cooling Tower located on the roof, three (3) Plate & Frame
Heat Exchangers utilized for "free cooling", tenant's condenser
water system fan coil units and radiant cooling floor system. All
water-cooled air conditioning units will use a R-410a or R407c
refrigerant to meet the requirements for LEED Certification (Green
Building). All chilled and condenser water pumps are equipped with
Variable Speed Drives to optimize energy consumption.
Humidification system:
Steam-to-steam humidifiers integrated with a Building Management
System (BMS) are installed in field assembled air handling units
supplying air into each floor.